BOSEN CCPP/120 MW Natural Gas Fired CCPP (2xGE LM6000 PD SPRINT GTG + lxSTG)

BOSEN had mandated ENPRODE Engineering as Basic and Detail Engineering Contractor for the new 120 MW Power Plant investment. The Power plant is located within BOSEN’s existing plot area in Bursa Organized Industrial Zone. Design was based on gas turbine combined cycle technology and encompassed two aero derivative gas turbines, one steam turbine, two vertical gas flow, drum type HRSGs and one mechanical draft cooling tower which had enough capacity to serve the new plant as well as the already installed units. BOSEN is a subsidiary of the Bursa Organized Industrial Zone and had already 130 MW installed capacity under operation. The new plant was the third capacity expansion investment of BOSEN. The first combined cycle with 60 MW capacity had been commissioned in 1999 and total capacity was increased to 130 MW with a second investment in 2006. Bursa Organized Industrial Zone is one of the largest industrial complexes in Turkey, constructed on 3,156 hectare area and having 959 active companies therein providing over 100.000 jobs.

Overall Plant Data

Gross power output120 MWe
Gross electrical efficiency52%
Emissions:
Nox50 mg/Nm3
Fuel TypeNatural gas

Gas Turbine

TypeGeneral Electric LM6000 PD Sprint
Site rating46500 kWe
Exhaust gas flow473.4 t/h
Exhaust gas temperature449.7 °C

Heat Recovery Steam Generator

TypeVertical, Drum Type Steam Turbine
Heat exchanger (HP)Mix Eco, Eco, Boiler, Superheater
Heat exchanger (LP)Mix Eco, Boiler

Steam Turbine

TypeMulti-Stage Condensing Steam Turbine
HP steam55 bar / 425°C
LP steam3.8 bar / 220°C
ST power output28 MWe
OwnerBOSEN ENERGY
LocationBursa / TURKEY
StatusCompleted

ENPRODE Project Responsibllities

  • Basic and Detail Engineering & Design
  • Procurement Consulting
  • Construction Management
  • Start-up and Commissioning

Power Plant Key

A Gas Turbine #1
BBy-pass Stack #1
CHeat Recovery Steam Generator # 1
DGas Turbine #2
EBy-pass Stack #2
FHeat Recovery Steam Generator #2
GSteam Turbine Building
HCooling Tower
IStep-Up Transformers