DELTA II CCPP / Natural Gas Fired CCPP (2xGTG + lxSTG)

ENPRODE Project Responsibilities

• Conceptual Design
• Basic and Detail Engineering
In April 2012 ENPRODE was awarded the contract for Conceptual Design, Basic and Detail Engineering Services of capacity extension project by DELTA Energy A.S., a subsidiary of PALMET Group of Companies (www.palmet. com), -130 MW additional capacity to increase the total installed capacity to about 200 MW. The Plant is located adjacent to the existing 62 MW Combined Cycle Power Plant (DELTA CCPP) in Büyükkarıştıran, Lüleburgaz, Kırklareli in the Thrace Region of Turkey. Engineering, Procurement and Construction Management (EPCM) contract of the existing 62 MW CCPP was also awarded to ENPRODE. ENPRODE managed & executed the project successfully in full compliance with environmental and technical standards. The existing plant has been in operation since 2009.

Design for extension encompasses the followings: Two (2) Gas Turbine Generator Packages (GTG), one (1) Steam Turbine Generator (STG), two (2) Heat Recovery Steam Generators (HRSG) and also one Air Cooled Condenser (ACC) in accordance with the equipment performance.

The project was executed in two consequential phases. The plant started commercial operation in Simple Cycle mode while erection works of the HRSG, ST and ACC were progressing for the Combined Cycle mode.

OwnerDELTA ENERGY (Palmet Group)
LocationKırklareli, Turkey
StatusCompleted